Purchasing
Order enough to reach your target stock position (daily sales x lead time + cover wanted + buffer), subtract what you hold and have on order, then round up to the case pack. If the MOQ is bigger, you are buying extra cover with cash, so price that cash and the extra days before you accept it. EOQ, Q = sqrt(2DS/H), is a sanity check for small stores, not the answer.
By Vishruth, Founder, Tenpo AI
10 min read

Take daily sales x (lead time + days of cover you want + buffer days), subtract stock on hand and on order, and round up to the supplier’s case pack. That is the order. If the supplier’s minimum order quantity (MOQ) is larger, the extra units are cash you are choosing to tie up. To run the numbers for a product in a minute, use the free order quantity calculator; the rest of this guide shows the maths behind it, including EOQ and price breaks.
Key points
Order quantity = daily sales x (lead time + cover days + buffer days) - on hand - on order, rounded up to the case pack.
When the MOQ binds, work out the extra units, the extra cash and the extra days of cover. Then pick the cheapest way to shrink the extra.
EOQ, the square root formula, assumes steady demand and no MOQ. Use it to check your plan, not to set it.
A price break only wins if the cash it ties up would not earn more elsewhere in the business.
How many units should you order from a supplier?
Enough to cover the wait for delivery, the stretch until your next order, and a buffer for lateness. Everything already in stock or on a boat counts against it.
Here is an example product (all numbers are examples, use your own): 8 units a day, a 35-day lead time, 30 days of cover wanted after the goods land, a 10-day buffer, 120 units on hand, nothing on order, $8.00 landed cost per unit, case pack of 50.
Target stock position: 8 x (35 + 30 + 10) = 600 units.
Subtract what you have: 600 - 120 - 0 = 480 units.
Round up to the case pack of 50: 500 units.
Cash: 500 x $8.00 = $4,000. Cover: (120 + 500) / 8 = 77.5 days from today.
Use landed cost, not the factory price, or the cash figure will be low (the landed cost guide covers freight, duty and fees). For the buffer, size it from how late deliveries actually run; the safety stock formula shows how, and the reorder point calculator tells you when to place the order in the first place.
What if the MOQ is bigger than what you need?
Then the order is the MOQ, and the real question is what the extra units cost you in cash and in days. Suppose the supplier’s MOQ is 800 against a plan of 500.
Extra units: 800 - 500 = 300.
Extra cash: 300 x $8.00 = $2,400, so $6,400 instead of $4,000.
Extra cover: 300 / 8 = 37.5 days. Total cover becomes (120 + 800) / 8 = 115 days.
Interest-style cost of holding the extra: at an example 25% a year for carrying stock, $2,400 x 25% x 37.5 / 365 = about $62.
That last number is small, and it misleads if you stop there. The real cost of the extra stock is that $2,400 is not available for ads or the next product, and that demand might change before you sell it. Check whether the 115 days fits the product’s life: a seasonal item, an item with an expiry date or something you may redesign should not get 37 extra days.
You have six ways to shrink the gap. Which one fits depends on the supplier.
Take it and cut the next order. The extra 300 units are not wasted, they are a prepayment. Next order, subtract the 300 from the plan. This is the default when demand is steady.
Split the MOQ across variants. If the MOQ is 800 per style but the supplier will count colors or sizes together, three variants needing 250 each (750) fit a mixed MOQ of 800. In an r/ecommerce thread, a founder was quoted a minimum of 100 per color across 5 colors, 2,000 units in total before any sale. The advice there was to launch one or two colors and expand once sales show which move.
Ask what drives the MOQ. One supply chain commenter in the r/smallbusiness thread said the MOQ is often a raw material lot or a packaging print run, not the production line, and that part can sometimes be bought separately. They also suggested a blanket order: commit to 1,500 units over 12 months at the 500-unit price, released in three drops, with the deposit paid per release. Suppliers differ, so treat both as questions to ask.
Pay a premium for a smaller run. Another commenter in that thread said many suppliers will do a split run of 200 to 300 units for a few dollars more per unit. With an example quote of 500 units at $8.80 instead of 800 at $8.00, you pay 500 x $8.80 = $4,400, which is $400 more than the plan at $8.00 but $2,000 less cash than the MOQ.
Run a paid trial or stagger delivery. In the r/ecommerce thread, a replier suggested a trial at a slightly higher unit cost, or full-MOQ production delivered in stages so the whole lot is not in your space at once.
Air a small first batch. If the product is hot and the ocean order is far off, air-freight a small quantity to cover the gap. Air only pays when the margin per unit is much larger than the extra freight per unit; check it with your landed cost.
Payment terms change how much cash is actually tied up, and when. A commenter in the same thread suggested 30% deposit and 70% before shipping instead of 100% upfront. Terms vary by supplier and product, so ask for them in writing. On a $6,400 order that example split is $1,920 at order and $4,480 before shipping.
How much cash does an order tie up, and when do you get it back?
The cash is out the moment you pay and comes back one sale at a time, so count both the wait and the time on the shelf. A simple version: cash-to-cash days = lead time + average days on the shelf.
For the 500-unit plan, average days on the shelf is half the order divided by daily sales: (500 / 2) / 8 = 31 days. Add the 35-day lead time and the average dollar is out about 66 days. For the 800-unit MOQ the shelf part grows to (800 / 2) / 8 = 50 days, so about 85 days.
Then compare it with what the cash earns. At an example $22 selling price and $8 landed cost, gross profit is $14 a unit. The $4,000 plan is paid back by sales in 4,000 / (8 x 22) = 22.7 days of selling after the goods land. The extra $2,400 of the MOQ takes another 13.6 days of sales to recover (2,400 / 176) on top of that, and it only returns if the units sell at the planned rate.
One commenter in the r/smallbusiness thread said that with a 4-month lead time, cash sits in a batch for something like 6 months before it comes back. That is one person’s estimate, but the shape holds: long lead times and big batches multiply the cash you need, and they advised checking profit per unit after fees, shipping and ads before borrowing against stock.

What is EOQ, and does it apply to your store?
Economic order quantity is the order size that minimizes the combined ordering and holding cost, and for most stores with MOQs it is a sanity check rather than a rule. The standard formula is Q = sqrt(2DS/H), where D is annual demand in units, S is the fixed cost of placing one order, and H is the annual cost of holding one unit. Wikipedia’s EOQ page writes it with K and h and lists the assumptions: constant demand, each order delivered in full when stock hits zero, a fixed cost per order, and one item per order. It also notes that the result does not depend on the unit price, and that transport rates and quantity discounts complicate real use.
Worked example, same product (example inputs): D = 8 x 365 = 2,920 units a year. S = $60 per order (an example for admin, inspection and a fixed freight booking fee). H = 25% of $8.00 = $2.00 per unit per year.
2 x 2,920 x 60 = 350,400.
350,400 / 2 = 175,200.
sqrt(175,200) = 419 units.
The EOQ is about 419 units, ordered roughly every 52 days, which is $3,349 of cash. Our cover-days plan said 500. Those are close, which is the useful part: if EOQ said 150 or 2,500, you would check your inputs.
Why it rarely sets the number for you:
MOQ and case packs. EOQ ignores them. If your MOQ is 800, EOQ’s answer of 419 is not on the table.
Lead time and lateness. The formula says how big, not when, and it assumes goods land exactly when stock hits zero. Real overseas orders do not.
Steady demand. Promotions, seasons and Chinese New Year break it. If you place orders ahead of the holiday, see the Chinese New Year order deadline guide.
Is a quantity discount worth taking?
Only if the unit saving beats the holding cost and the cash cost of the bigger lot. Compare total annual cost, not just unit price. Total cost = price x D + S x D / Q + H x Q / 2, where H is 25% of the unit price at each tier.
Example price breaks for the same product, D = 2,920 and S = $60:
300 units at $8.60: purchase $25,112, ordering $584, holding $322, total $26,018. Cash per order $2,580.
500 units at $8.00: purchase $23,360, ordering $350, holding $500, total $24,210. Cash per order $4,000.
1,000 units at $7.40: purchase $21,608, ordering $175, holding $925, total $22,708. Cash per order $7,400.
2,000 units at $7.00: purchase $20,440, ordering $88, holding $1,750, total $22,278. Cash per order $14,000.
On paper the 2,000 tier is cheapest. Look at what each step buys. Moving from 500 to 1,000 saves $1,502 a year for $3,400 more cash per order. Moving from 1,000 to 2,000 saves $430 a year for $6,600 more cash per order, and 2,000 units is 265 days of cover with the stock on hand. The first step can be worth it if the cash is idle. The second is $430 of saving against tying up $14,000, and it bets on demand holding for nine months. Holding cost is already in the totals, but the risk of stale stock and the ads the cash could have funded are not.
A prompt you can paste
Paste this into ChatGPT or Claude with your sales export and supplier terms. It reproduces the calculation above, so you can check the output by hand.
I buy a product from an overseas supplier. My inputs: daily sales (last 28 days) = [x]; lead time in days = [x]; cover days wanted after arrival = [x]; buffer days = [x]; stock on hand = [x]; stock on order = [x]; case pack = [x]; MOQ = [x]; landed unit cost = [x]; annual holding rate = [x%]; fixed cost per order = [x].
Calculate: target stock position = daily sales x (lead time + cover days + buffer days); order quantity = target - on hand - on order, rounded up to the case pack; if the MOQ is larger, show the extra units, extra cash and extra days of cover.
Then calculate EOQ = sqrt(2 x annual demand x fixed cost per order / (holding rate x landed unit cost)) as a reference only. Show every formula with the numbers substituted, tell me which of the two is larger, and do not invent any figures I did not give you.
What should you do this week?
Take your three biggest purchase lines and compute the order quantity and cash each needs.
Where the MOQ binds, write down the extra units, extra cash and extra days, then try one of the six levers before you accept it.
Check any price break by total annual cost and by the cash it ties up, not by unit price alone.
Reduce the next order by any extra units you took, so the surplus becomes cover instead of a pile.
Where Tenpo fits
Tenpo is our product, so weigh this accordingly. Otto, the operations employee, reads stock cover for each product and open purchase orders, and can draft a reorder and the purchase order for you to approve; supplier follow-ups go out from your own mailbox only after you say yes. Your MOQ, deposit terms and the cash-versus-cover choice stay yours: check each supplier quote against the maths above before you approve. It connects to Shopify today. Plans start at $79 a month for one store and $199 a month for up to three. You can try Tenpo or see the plans.
Related
Sources
r/smallbusiness: How do you scale when each batch doesn’t pay for the next one’s MOQ?
All dollar figures, unit counts and tiers in the worked examples are examples computed for this guide.